PROJECT OVERVIEW

The Challenges

The static strength of two quay cranes was checked for loads and trolley positions during the normal working cycle. Five different trolley positions were analyzed.

Based on the analysis results, recommendations regarding reinforcement or modification of crane elements and joints were issued.

Two quay cranes were surveyed.

STRUCTURAL VERIFICATION

FEM Analysis of Two Quay Cranes

FEM analysis was performed to assess the static strength of two quay cranes for loads and trolley positions during the normal working cycle.

>   Multiple Trolley Positions
Analysis was performed for five trolley positions during the normal working cycle.
>   Static Strength
Verification of the static strength of the crane structures under the defined load cases.
>   Structural Elements and Joints
Assessment of crane elements and joints based on the analysis results.
>   Recommendations
Recommendations for reinforcement or modification of crane elements and joints were issued.

PROJECT OUTCOME

Structural Assessment and Recommendations

The structural analysis provided verification of the static strength of two quay cranes for loads and trolley positions during the normal working cycle. Five trolley positions were analyzed, and recommendations regarding reinforcement or modification of crane elements and joints were issued based on the obtained results